Factory Calendar Settings Affecting MRP and Work Orders

Issue Description:

Planning Work Orders cannot be created or scheduled on Saturdays and Sundays because these days are marked as holidays in the Factory Calendar.

Root Cause:

Weekends or other non-working days are defined as holidays in Factory Calendar, which prevents scheduling or visibility of Work Orders and MRP items.

Solution :

1.Go to Administration > System Initialization > Factory Calendar

2.Change Saturday and Sunday from Holidays to Working Days.

3.Save the Factory Calendar.

Symptoms:
  • Semi-Finished Goods Missing in MRP