Factory Calendar Settings Affecting MRP and Work Orders
Issue Description:
Planning Work Orders cannot be created or scheduled on Saturdays and Sundays because these days are marked as holidays in the Factory Calendar.
Root Cause:
Weekends or other non-working days are defined as holidays in Factory Calendar, which prevents scheduling or visibility of Work Orders and MRP items.
Solution :
1.Go to Administration > System Initialization > Factory Calendar
2.Change Saturday and Sunday from Holidays to Working Days.
3.Save the Factory Calendar.
Symptoms:
- Semi-Finished Goods Missing in MRP